The formula
Volume = (bottom + top width) ÷ 2 × depth × length.
What it works out
Excavated volume, loose spoil and backfill for a trench.
Why it matters
Plan the excavator, trucks and backfill material.
How to use it
- Enter the Trench Length, the Bottom Width and the Depth in metres.
- Choose a Side Slope: Vertical (shored) for a supported trench, or a 1:0.5, 1:1 or 1:1.5 slope for open cut in stiff, average or loose soil.
- Enter the Pipe Diameter in millimetres, so the pipe volume is taken off the backfill. Use 0 if there is no pipe.
- Set Soil Swell (%) and Backfill Compaction Allowance (%). The defaults are 25% and 15%.
- Read Top Width, Excavated Volume, Loose Spoil, Pipe Volume and Backfill to Order.
Quick reference
Printable chartTrench volume by depth (50 m long, 0.8 m wide, vertical sides)
| Depth (m) | Excavated (m³) | Loose spoil (m³) | Backfill to order (m³) |
|---|---|---|---|
| 1 | 40 m³ | 50 m³ | 41.94 m³ |
| 1.2 | 48 m³ | 60 m³ | 51.14 m³ |
| 1.5 | 60 m³ | 75 m³ | 64.94 m³ |
| 2 | 80 m³ | 100 m³ | 87.94 m³ |
| 2.5 | 100 m³ | 125 m³ | 110.9 m³ |
| 3 | 120 m³ | 150 m³ | 133.9 m³ |
A 50 m shored trench, 0.8 m wide, with a 300 mm pipe, 25% swell and 15% compaction allowance. Change the inputs above for your trench.
The formula
Top width = bottom width + 2 × depth × slope. Excavated volume = (bottom width + top width) ÷ 2 × depth × length. Loose spoil = excavated volume × (1 + swell ÷ 100). Backfill to order = (excavated volume − pipe volume) × (1 + compaction ÷ 100). The pipe volume is π × radius² × length.
What changes the result
The side slope has the biggest effect on a deep trench: at 1:1 the top is wider than the bottom by twice the depth, so the volume grows quickly. Swell sets how many truckloads leave the site, since dug soil takes up more room than it did in the ground. The compaction allowance covers the extra loose material needed to end up with compacted fill at the original volume. The pipe is deducted from backfill, but bedding and surround material are not separated, so add them if they are a different material.
Trenching practice on UAE sites
Deep trenches need shoring or sloping, and many sites require support from around 1.2 to 1.5 m depth; follow your contractor’s method statement and the local authority rules. High groundwater and sabkha ground in coastal areas often mean dewatering, which this calculator does not cover. Plan the excavator, the tippers for spoil and the backfill delivery together, because the spoil you haul out is rarely the material you bring back.
Worked examples
- A 50 m shored trench, 0.8 m wide and 1.5 m deep, is 60 m³ in the ground. Haul away 75 m³; the 300 mm pipe takes 3.53 m³, so order 64.94 m³ of backfill.
- A 120 m open-cut trench at 1:1 slope, 1 m wide at the bottom and 2 m deep, is 5 m wide at the top and 720 m³ excavated.
- A 200 m cable and duct trench, 0.6 m wide and 1 m deep, needs 129.9 m³ of backfill and 144 m³ of spoil removal.
Frequently asked questions
How do I calculate trench volume?
For a trench with sloped sides, add the bottom and top widths, halve the sum, then multiply by the depth and the length. With vertical sides it is simply width × depth × length.
How do I calculate trench backfill?
Take the excavated volume, subtract the volume of the pipe, then add an allowance for compaction. The calculator shows this as Backfill to Order.
How much extra do I need for compaction?
Loose fill compacts down, so you order more than the hole holds. 10 to 20% is common; the calculator defaults to 15%. Your geotechnical report or supplier can give a better figure.
What is swell in a trench?
Soil takes up more space once it is dug. A swell of 20 to 30% is typical, so the loose spoil you haul is larger than the trench volume.
What side slope should I use?
Use Vertical only when the trench is shored. For open cut, 1:0.5 suits stiff soil, 1:1 average soil and 1:1.5 sand or loose soil. The competent person on site decides the actual slope.
Add this calculator to your website
Copy the code and paste it into your page. The calculator is free and works as it does here.
<iframe src="https://www.equipmentsfinder.com/embed/field-tools/trench-volume-calculator" title="Trench volume and backfill calculator" width="100%" height="620" style="border:0;max-width:720px" loading="lazy"></iframe> <p style="font-size:12px"><a href="https://www.equipmentsfinder.com/field-tools/trench-volume-calculator">Trench volume and backfill calculator</a> by <a href="https://www.equipmentsfinder.com">EquipmentsFinder</a></p>