EF Logo

Dump truck capacity calculator: how many truckloads?

How many truckloads does the job take? Enter the volume, the material and the truck, and the calculator checks both the body volume and the payload limit.

The formula

Loads = the larger of loose volume ÷ body volume and weight ÷ payload.

What it works out

How many dump truck loads a job takes.

Why it matters

Book the right number of trucks and trips.

How to use it

  1. Enter Material to Move (in place) in m³: the volume as measured in the ground or in the design.
  2. Choose the Material. It sets the density in t/m³ for gravel, sand, aggregate, road base, topsoil, fill or asphalt.
  3. Set Swell When Loaded (%), the extra space the material takes once it is dug. The default is 25%.
  4. Enter the Truck Body Volume in m³ and the Truck Payload in tons. The defaults are 16 m³ and 25 t.
  5. Read Loads by Volume and Loads by Weight, then use Truckloads Needed, which is the larger of the two.

Quick reference

Printable chart

Truckloads by volume (fill at 1.5 t/m³, 16 m³ body, 25 t payload)

Volume (m³)Weight (t)Loads by volumeLoads by weightTruckloads needed
100150 t8 loads6 loads8 loads
250375 t20 loads15 loads20 loads
500750 t40 loads30 loads40 loads
1,0001,500 t79 loads60 loads79 loads
2,0003,000 t157 loads120 loads157 loads
5,0007,500 t391 loads300 loads391 loads

Fill at 1.5 t/m³ with 25% swell, hauled in 16 m³ tippers with a 25 t payload. Change the inputs above for your material and truck.

The formula

Material weight = volume × density. Loose volume = volume × (1 + swell ÷ 100). Loads by volume = loose volume ÷ body volume, and loads by weight = material weight ÷ payload, each rounded up. Truckloads needed is the larger of the two, because a truck is full when it reaches either limit.

Why there are two limits

Light material, such as topsoil, fills the body before it reaches the legal payload, so volume decides the number of loads. Heavy material, such as road base or asphalt, hits the payload long before the body is full, so weight decides. The calculator shows both and picks the one that governs. Swell matters for volume only: a cubic metre of dug soil takes up more space in the body, but it does not weigh more.

Hauling practice on UAE sites

Typical tippers carry about 16 to 20 m³ and 20 to 30 tons, but check the truck’s registration and the payload limit rather than using a rule of thumb. Overloaded trucks are fined and refused at weighbridges and disposal sites, so do not fill past the limit just to save a trip. Loads also depend on the haul distance and the loading rate, so size the loader or excavator to match the number of trucks, and agree the disposal site and its opening hours before you book.

Worked examples

  • 500 m³ of fill weighs 750 t and is 625 m³ once loaded. That is 40 loads by volume and 30 loads by weight, so book 40 loads.
  • 300 m³ of road base in 20 m³ tippers with a 25 t payload: the weight is 600 t, so weight sets the number at 24 loads against 18 loads by volume.
  • 1,200 m³ of topsoil is 1,500 t but 1,560 m³ loose, so volume governs: 98 loads by volume against 60 loads by weight, giving 98 loads.

Frequently asked questions

How many truckloads do I need?

Work out the loose volume and the weight of the material, divide each by the truck’s body volume and payload, and take the larger number. The calculator above does this and shows Truckloads Needed.

How do I use a dump truck capacity calculator?

Enter the volume of material, pick the material, set the swell, and enter the truck’s body volume and payload. Compare Loads by Volume with Loads by Weight; the larger one is the number you need.

What is the capacity of a typical UAE tipper?

Around 16 to 20 m³ of body volume and 20 to 30 tons of payload, depending on the axle layout. Ask the supplier for the actual figures of the truck being sent.

What is swell when loading a truck?

Material is looser once it is dug than it was in the ground, so it fills more of the body. A swell of 20 to 30% is common for soil and fill.

Why are the loads by volume and by weight different?

Because a truck is limited by both its body size and its legal payload. Light material fills the body first; heavy material reaches the payload first. The larger number governs.

Add this calculator to your website

Copy the code and paste it into your page. The calculator is free and works as it does here.

<iframe src="https://www.equipmentsfinder.com/embed/field-tools/dump-truck-load-calculator" title="Dump truck capacity calculator: how many truckloads?" width="100%" height="620" style="border:0;max-width:720px" loading="lazy"></iframe>
<p style="font-size:12px"><a href="https://www.equipmentsfinder.com/field-tools/dump-truck-load-calculator">Dump truck capacity calculator: how many truckloads?</a> by <a href="https://www.equipmentsfinder.com">EquipmentsFinder</a></p>
EquipmentsFinder

Need equipment? Have equipment?

Buyers post one request and get quotes from suppliers. Suppliers list free and reach active demand.