The formula
m³/h = (drum width − overlap) × speed × 1,000 × layer × efficiency ÷ passes.
What it works out
Work out how much fill a roller can compact per hour and per day.
Why it matters
Match the roller to the pace of the grader or spreader, so the layer is rolled before it dries.
How to use it
- Enter the Drum Width and the Overlap Between Passes. Overlap of 10 to 30 cm is normal.
- Enter the Rolling Speed in km/h. Vibratory rollers on soil work at about 3 to 6 km/h.
- Enter the Compacted Layer Thickness in cm and the Passes Needed, from your specification or a test strip.
- Set the Job Efficiency, the Hours per Day, and the Daily Fill to Place if you want to know how many rollers it needs.
Quick reference
Printable chartRoller output by number of passes (2.1 m drum, 4 km/h, 30 cm layer)
| Passes | Output (m³/h) | Area (m²/h) | Per day (m³) |
|---|---|---|---|
| 4 | 427.5 m³/hr | 1,425 m²/hr | 3,420 m³/day |
| 6 | 285 m³/hr | 950 m²/hr | 2,280 m³/day |
| 8 | 213.8 m³/hr | 712.5 m²/hr | 1,710 m³/day |
| 10 | 171 m³/hr | 570 m²/hr | 1,368 m³/day |
| 12 | 142.5 m³/hr | 475 m²/hr | 1,140 m³/day |
A 2.1 m drum with 20 cm overlap, 4 km/h, 30 cm layers and 75% efficiency.
The formula
Area per hour = (drum width − overlap) × speed × 1,000 × efficiency ÷ passes, in m² when the width is in m and the speed in km/h. Volume per hour = area per hour × compacted layer thickness. Rollers needed = daily fill ÷ daily output, rounded up. The volume is compacted volume, so it is the fill that ends up in the embankment.
Layer thickness and passes
The layer thickness and the number of passes are set by the earthworks specification and the roller’s weight and vibration, not by the calculator. Thicker layers are quicker per m³ but may not reach the density at the bottom. Run a test strip, check the density, and then enter the passes and thickness that pass. Moisture matters more than the number of passes: soil that is too wet or too dry will not compact however many passes it gets.
Keeping up with the spread
A roller that is too slow lets the spread layer dry out and gets blocks of un-rolled fill; one that is too fast leaves the grader and trucks waiting on it. Use the rollers-needed figure to match the compaction to the pace of the fill. In the Gulf heat, a spread layer loses moisture quickly, so keep a water tanker close and roll soon after spreading. Efficiency of about 75% allows for turning at the ends, watering and checks.
Worked examples
- A 2.1 m drum rolling 30 cm layers at 4 km/h in 6 passes compacts 285 m³/hr, covering 950 m²/hr. That is 2,280 m³/day a day, so 1 rollers cover a 1,500 m³ daily fill.
- A smaller 1.7 m roller on 20 cm layers at 3 km/h and 8 passes does 84.38 m³/hr, or 675 m³/day a day: 2 rollers for 800 m³.
- With 40 cm layers in 4 passes at 5 km/h, a 2.2 m drum reaches 800 m³/hr; for 5,000 m³ a day you need 1 rollers.
Frequently asked questions
How do I calculate roller productivity?
Multiply effective drum width by speed and layer thickness, then by efficiency, and divide by the number of passes.
How many passes does a roller need?
It depends on the soil, the roller and the specified density. A test strip gives the number; 4 to 8 passes is common for soil.
What speed should a roller work at?
Vibratory soil compactors work at about 3 to 6 km/h; slower gives more effect per pass.
Why is the volume lower than I expected?
Passes divide the output directly: doubling the passes halves it. Overlap and efficiency also reduce it.
Is this loose or compacted volume?
Compacted, as laid in the fill. Use the soil swell calculator to convert it to loose volume to haul.
Add this calculator to your website
Copy the code and paste it into your page. The calculator is free and works as it does here.
<iframe src="https://www.equipmentsfinder.com/embed/field-tools/compaction-production-calculator" title="Compaction production calculator: roller output per hour" width="100%" height="620" style="border:0;max-width:720px" loading="lazy"></iframe> <p style="font-size:12px"><a href="https://www.equipmentsfinder.com/field-tools/compaction-production-calculator">Compaction production calculator: roller output per hour</a> by <a href="https://www.equipmentsfinder.com">EquipmentsFinder</a></p>