The formula
Loose m³/h = blade × 60 ÷ cycle × efficiency × grade factor × material factor.
What it works out
Estimate a dozer’s output from its blade, push distance, speeds and the ground.
Why it matters
Plan how many dozer hours a cut, spread or stockpile job needs.
How to use it
- Enter the Blade Capacity in loose m³ from the manufacturer’s spec (SAE or heaped, for the blade fitted).
- Enter the Push Distance and the Forward and Return speeds. Use real working speeds, not the top gear.
- Leave Fixed Time at 0.05 min for a power-shift dozer or change it if you know your machine’s turn and gear-change time.
- Set the Grade (positive uphill), the Material and the Job Efficiency. A 50-minute working hour is 83%.
- Read Loose Production and Bank Production per hour, and the Daily Bank Production.
Quick reference
Printable chartOutput by push distance (6 m³ blade, level, average soil)
| Push distance (m) | Cycle (min) | Loose (m³/h) | Bank (m³/h) |
|---|---|---|---|
| 20 | 0.4881 min | 612.2 m³/hr | 489.7 m³/hr |
| 40 | 0.9262 min | 322.6 m³/hr | 258.1 m³/hr |
| 60 | 1.36 min | 219 m³/hr | 175.2 m³/hr |
| 80 | 1.8 min | 165.8 m³/hr | 132.6 m³/hr |
| 100 | 2.24 min | 133.4 m³/hr | 106.7 m³/hr |
| 150 | 3.34 min | 89.58 m³/hr | 71.66 m³/hr |
A 6 m³ blade at 4.5 km/h forward, 7 km/h back, 83% efficiency and 25% swell.
The method
Cycle time = push distance ÷ forward speed + push distance ÷ return speed + fixed time. Loose production = blade capacity × 60 ÷ cycle time × job efficiency × grade factor × material factor. Bank production = loose production ÷ (1 + swell). This is the same layout as the manufacturers’ performance handbooks, such as the Caterpillar Performance Handbook, which also publish blade-load charts for each model. Use their figures for your machine where you have them.
The correction factors
The grade factor here is a straight-line approximation to the handbook’s curve: about 2% less for each 1% uphill and 1.5% more for each 1% downhill, kept between 0.4 and 1.3. Material factors follow the handbook categories: a loose stockpile 1.2, average soil 1.0, hard or packed material 0.8, ripped or blasted rock 0.7. Job efficiency covers operator skill, waiting for trucks, weather and maintenance; 83% is a 50-minute hour, and heat and dust in a Gulf summer often justify less.
Limits of the estimate
Dozing is best below about 100 m and economic only to about 150 m; beyond that a scraper or an excavator with trucks is cheaper per m³. The result assumes the blade carries its rated load: slot dozing, side-by-side blades and a well-prepared push path raise it, and a poorly cut or wet surface lowers it. Time a few real cycles on the job and adjust the efficiency to match.
Worked examples
- A 6 m³ blade pushing 60 m on the level has a 1.36 min cycle and moves 219 m³/hr, which is 175.2 m³/hr in the ground, or 1,402 m³/day in an 8-hour day.
- A 9 m³ blade pushing hard material 100 m up a 10% grade has a grade factor of 0.8 and produces 128 m³/hr, or 102.4 m³/hr bank.
- A small 4 m³ dozer pushing a loose stockpile 40 m downhill at 8% moves 289.1 m³/hr, which is 1,850 m³/day a day.
Frequently asked questions
How do I calculate dozer production?
Blade capacity times cycles per hour, then times job efficiency, grade factor and material factor. The calculator does each step.
How many cubic metres per hour does a bulldozer move?
A mid-size dozer on a 60 m push moves roughly 100 to 200 loose m³ an hour, depending on blade, material and efficiency. Enter your own figures above.
What is the difference between loose and bank production?
Loose is the volume as pushed, bank is the same soil measured in the ground. Excavation is usually paid in bank volume.
What is the economic push distance of a dozer?
Up to about 100 m is where a dozer is at its best; beyond about 150 m other methods usually cost less.
What job efficiency should I use?
83% is a 50-minute hour and a common starting point. Lower it for poor conditions or an inexperienced crew.
Add this calculator to your website
Copy the code and paste it into your page. The calculator is free and works as it does here.
<iframe src="https://www.equipmentsfinder.com/embed/field-tools/dozer-production-calculator" title="Dozer production calculator: cubic metres per hour" width="100%" height="620" style="border:0;max-width:720px" loading="lazy"></iframe> <p style="font-size:12px"><a href="https://www.equipmentsfinder.com/field-tools/dozer-production-calculator">Dozer production calculator: cubic metres per hour</a> by <a href="https://www.equipmentsfinder.com">EquipmentsFinder</a></p>