Excavation volume calculator

Calculate the volume of a trench, pit or basement excavation in cubic metres, with an allowance on top, to plan trucks, disposal and excavator time.

How to use it

  1. Enter the Length and Width of the excavation in metres.
  2. Enter the Depth in metres, measured from the starting level to the formation level.
  3. Set Wastage (%) for over-dig, working space and swell. The default is 5%.
  4. Read Base Volume (the exact in-ground volume) and Total Volume (with the allowance). Use the Total Volume for trucks and disposal.

The formula

Base volume = length × width × depth. Total volume = base volume × (1 + wastage ÷ 100). With dimensions in metres the result is in cubic metres (m³).

What changes the result

This is a box calculation, so it assumes vertical sides and a flat bottom. Sloped sides, benching and working space around foundations add volume: use the average length and width of the excavation, or add them to the dimensions. Excavated soil also swells (bulks) once loosened, so it fills more truck volume than it took up in the ground; raise the percentage to cover that when sizing haulage.

Earthwork practice on UAE sites

Volumes are normally measured in the ground (bank cubic metres) for payment and in loose volume for trucking, so be clear which one the number is for. Excavation near services, a high water table or sabkha ground in coastal areas can change the method and the quantity, and the site investigation report is the place to check. Plan the excavator, the dump trucks and the disposal route together.

Worked examples

  • A 20 m × 8 m pit dug 2 m deep is 320 m³ in the ground; allow 336 m³ for trucking and disposal.
  • A 100 m pipe trench, 1.2 m wide and 1.5 m deep: 180 m³ base, 189 m³ with the allowance.
  • A 30 m × 20 m basement 4 m deep with 10% for swell and over-dig: 2,640 m³ to haul away.

Excavation volume by depth (20 m × 8 m)

Printable chart
Depth (m)In the ground (m³)With 5% allowance (m³)
0.580 m³84 m³
1160 m³168 m³
1.5240 m³252 m³
2320 m³336 m³
2.5400 m³420 m³
3480 m³504 m³
4640 m³672 m³
5800 m³840 m³

A 20 m × 8 m excavation with a 5% allowance. For another footprint, enter your own length and width above.

Frequently asked questions

How do I calculate excavation volume?

Multiply length × width × depth in metres. For sloped sides use the average length and width at mid-depth.

How do I calculate the volume of a trench?

Use the trench length, width and depth in the calculator above. Add the allowance for over-dig and swell.

What is bulking or swell in excavation?

Soil takes up more space once it is dug than it did in the ground. Raise the Wastage (%) to size trucks and disposal for the loose volume.

Does the calculator handle sloped sides?

No, it assumes straight sides. Use the average dimensions of the excavation, or split it into sections.

How many truckloads is my excavation?

Divide the Total Volume by the capacity of your truck in cubic metres, and round up. Check the truck capacity with the supplier.

Add this calculator to your website

Copy the code and paste it into your page. The calculator is free and works as it does here.

<iframe src="https://www.equipmentsfinder.com/embed/field-tools/excavation-volume-calculator" title="Excavation volume calculator" width="100%" height="620" style="border:0;max-width:720px" loading="lazy"></iframe>
<p style="font-size:12px"><a href="https://www.equipmentsfinder.com/en-us/field-tools/excavation-volume-calculator">Excavation volume calculator</a> by <a href="https://www.equipmentsfinder.com">EquipmentsFinder</a></p>